Bluewater Park Water System Replacement Project:
Final Stages July – August 2025
We are entering the final stages of the Bluewater Park Water System Replacement Project, with
roadwork and paving scheduled to take place through July and August 2025.
Paving Schedule
Full road-width paving will be carried out in two stages:
Stage One: Commencing July 16, 2025
- Windjammer Loop (including Privateer Road)
Stage Two: Commencing early August
- Remainder of Windjammer Road
- Captain’s Way
- Spyglass Road
- Clipper Place
- Forecastle Road
The work is anticipated to be complete by the end of August 2025.
Traffic Impacts
Please be advised that during constructions:
- Roadways will be reduced to single lane alternating traffic at times.
- Traffic controllers (flaggers) will be on-site to guide vehicles and ensure safety.
- Residents are asked to use caution, obey signage, and allow extra travel time as needed.
We appreciate your patience and cooperation as we complete these critical infrastructure improvements.
Questions? Contact Public Works at 604-947-4255 ext 3 or roads@bimbc.ca