Community Centre Update August 2022

We have walls! Over the past month at the Community Centre construction site, it’s been all about building forms for the foundation walls and pouring concrete. We’re starting to see the footprint of the building taking shape! This work is…

Community Centre Update June 2022

Community Centre update: forming the foundations of our community There’s a lot going on at the Community Centre construction site! It’s so exciting to see the building as it is formed from the ground up. Over the last couple of…

Community Centre Update February 2022

Celebrate community at a land blessing for the Community Centre The community is invited to come together to participate in a land blessing ceremony at the future home of the Community Centre on Tuesday, February 15 at 11:00 am. Special…

Community Centre Update December 17 2021

It’s happening! You’ve probably heard the fantastic news that we’ll soon be breaking ground to build the long-awaited Community Centre. The Bowen Island Municipality will be awarding a construction contract to Golden Globe Construction Ltd., with the project slated to…

Community Centre Update December 1 2021

BIM moving forward with construction of the Community Centre; Project budget updated to $18.7 m. Bowen Island Municipality has issued a letter of intent to award the construction contract for the Community Centre to Golden Globe Construction Ltd. for $14.4…

Community Centre Update September 2021

BIM receives promising results of Community Centre construction bidding After the close of a five-week competitive tendering process, the Community Centre project team is optimistic to have received three bids. While all three bids propose construction costs exceeding the project…